Richmond's $31.5 billion transportation plan

In September 2026 the Richmond region adopted Pathways to the Future: Transportation 2050. It plans about $31.5 billion through 2050. Most keeps existing roads and transit running; about $7.9 billion builds 121 new regional projects.

Last updated

Key takeaways

  1. Upkeep comes first. About 57% of the $31.5 billion, $18.0B, pays for maintenance and operations. Source: Technical Report I
  2. $7.9 billion for new regional projects. Highways and roads take about 72% of it; transit 18%; walking and biking 9% (shares are my arithmetic on the report's totals). Source: Technical Report I, Appendix D
  3. Most projects come late. 18 projects land in 2026–2031, 23 in 2032–2037 and 80 in 2038–2050. Source: Technical Report I, Appendix D
  4. Transit stays fare-free in the plan. It assumes GRTC's zero-fare policy continues and counts no fare revenue. Source: Technical Report I
  5. Henrico has the most projects: 58 of 127. Source: Technical Report I, Appendix D

Explore

Follow the money

1 of 4

Where the money comes from

Over 2026–2050 the region expects about $31.5 billion for transportation, from federal, state, regional (CVTA) and local sources. Source: PlanRVA, Transportation 2050

2 of 4

Most of it keeps what we have

About 57%, $18.0B, goes to maintenance and operations. Local projects get about 13%; regional projects about 30%. Source: Technical Report I

3 of 4

Some regional money is already spoken for

Of $9.57B in regional funds, $1.66B goes to projects already in the state's six-year program. That leaves about $7.9 billion for new projects. Source: Technical Report I

4 of 4

What the new money builds

Highways and roads take $5.71B across 86 projects. Transit gets $1.46B for 9 projects, including 6 bus rapid transit lines. Walking and biking get $677M for 21 projects; park and ride $41M for 5. Source: Technical Report I, Appendix D

Band widths are dollars (year-of-expenditure). Totals from PlanRVA Technical Report I.

When projects happen

Each band is a time period. Press one to show only its projects on the map.

2026–203118 projects9 highways and roads projects6 walking and biking projects3 park and ride projects$203M 2032–203722 projects17 highways and roads projects2 transit projects3 walking and biking projects$2.00B 2038–205080 projects59 highways and roads projects7 transit projects12 walking and biking projects2 park and ride projects$5.68B
120 new regional projects by time band and mode, with their total cost. Six bridge repair projects are funded from maintenance money and have no time band. Source: Technical Report I, Appendix D

Highways and roadsTransitWalking and bikingPark and rideBridges (repair)

Where they are

The map loads when you scroll here. Every project is also in the table below.

Showing all 125 mapped projects.

All 127 projects as a table
Transportation 2050 constrained projects
ProjectTypeLocalityYearsCost
Pouncey Tract Rd Widening - W Broad St to N Gayton RdHighways and roadsHenrico2026–2031$29M
West Vaughan Road Grade SeparationHighways and roadsAshland2026–2031$27M
Nine Mile Rd Safety - Gordons Ln to Dabbs House RdHighways and roadsHenrico2026–2031$25M
Route 1/Brook Rd Safety - Parham to Magnolia RidgeHighways and roadsHenrico2026–2031$17M
VA-10 & Walmsley BlvdHighways and roadsRichmond2026–2031$14M
Shared Use Path: East End/West Creek TrailWalking and bikingGoochland2026–2031$13M
Parham Rd Safety - St Charles Rd to Chamberlayne AveHighways and roadsHenrico2026–2031$11M
Cox Rd - Separated Bike LaneWalking and bikingHenrico2026–2031$10M
Lauderdale Dr Widening - Westbriar to EdenburyHighways and roadsHenrico2026–2031$10M
Shared Use Path: Nuckols Rd TrailWalking and bikingHenrico2026–2031$8M
I-64 at I-295 in Short Pump - New Park and Ride LotPark and rideHenrico2026–2031$8M
Willow Lawn/Staples Mill - New Park and Ride LotPark and rideHenrico2026–2031$7M
VA-54 Widening - Frances Rd to East Corporate LimitsHighways and roadsAshland2026–2031$7M
Shared Use Path: Wilton on the James TrailWalking and bikingHenrico2026–2031$6M
I-295 & Creighton Rd Interchange ModificationHighways and roadsHanover2026–2031$4M
US 288/US 250 Interchange - New Park and RidePark and rideGoochland2026–2031$3M
Shared Use Path: Fall Line Trail to VA Center CommonsWalking and bikingHenrico2026–2031$2M
Shared Use Path: VA-150 to Jessup RoadWalking and bikingChesterfield2026–2031$2M
Powhite Pkwy Extension Phase 2 - Woolridge Rd to US-360Highways and roadsChesterfield2032–2037$679M
North-South BRT Phase 1 - Azalea to Downtown to StonebridgeTransitMulti-Jurisdiction2032–2037$538M
Belvidere I-95/I-64 Interchange ImprovementsHighways and roadsRichmond2032–2037$108M
Western BRT Extension Phase 1 - Willow Lawn to ParhamTransitMulti-Jurisdiction2032–2037$87M
Shared Use Path: Fall Line Trail - Chesterfield SectionsWalking and bikingChesterfield2032–2037$82M
Powhite Pkwy/Charter Colony InterchangeHighways and roadsChesterfield2032–2037$81M
Shared Use Path: Fall Line Trail - Richmond SectionsWalking and bikingRichmond2032–2037$60M
U.S. Route 1 Safety - England St to Northern Town LimitHighways and roadsAshland2032–2037$49M
Ashland Road (Route 623) Widening - North of I-64Highways and roadsGoochland2032–2037$49M
Huguenot Rd Capacity & Safety - Robious Rd to Cranbeck RdHighways and roadsChesterfield2032–2037$43M
Patterson Ave Safety - Three Chopt to Pump RdHighways and roadsHenrico2032–2037$40M
Hull Street Intersection & Ped ImprovementsHighways and roadsRichmond2032–2037$36M
Rt. 33 Widening Ph. 1 - Chickahominy River to Winns Church RdHighways and roadsHanover2032–2037$28M
Creighton Rd Widening - I-295 to Cold Harbor RdHighways and roadsHanover2032–2037$21M
Three Chopt Rd Widening - Skipwith to HorsepenHighways and roadsHenrico2032–2037$20M
Andersons Highway Corridor Safety ImprovementsHighways and roadsPowhatan2032–2037$20M
Shared Use Path: Monument Ave - Willow Lawn to BremoWalking and bikingHenrico2032–2037$13M
US-1 & E Parham Rd Intersection ImprovementHighways and roadsHenrico2032–2037$13M
US-250 & Pouncey Tract Rd Intersection ImprovementHighways and roadsHenrico2032–2037$13M
Ashcake Road Grade SeparationHighways and roadsAshland2032–2037$12M
Woodman Rd Widening - Hermitage to HilliardHighways and roadsHenrico2032–2037$7M
I-295 Auxiliary Lane - I-95 SB Branch to Chamberlayne RdHighways and roadsHanover2032–2037$1M
Rt 288 SB (Powhite Pkwy - Route 360) CD Road ExtensionHighways and roadsChesterfield2038–2050$352M
Mechanicsville Turnpike BRTTransitMulti-Jurisdiction2038–2050$307M
Route 1 Great Streets ImprovementsHighways and roadsRichmond2038–2050$263M
I-64 & US-250 Interchange ImprovementsHighways and roadsHenrico2038–2050$260M
I-64 & Gaskins Rd Interchange ModificationHighways and roadsHenrico2038–2050$238M
Eastern BRT Airport Extension - Rocketts Landing to AirportTransitMulti-Jurisdiction2038–2050$175M
I-95 (Willis Road to Route 10) - Widening 6 to 8 LanesHighways and roadsChesterfield2038–2050$156M
North-South BRT (VCC to Azalea) Phase 2aTransitHenrico2038–2050$149M
Western BRT Extension Phase 2 - Parham to Short PumpTransitHenrico2038–2050$149M
Walmsley Boulevard Extension & Shared Use PathHighways and roadsRichmond2038–2050$144M
Woodman Rd Widening - Mountain to HungaryHighways and roadsHenrico2038–2050$140M
Bryan Park Interchange ImprovementsHighways and roadsRichmond2038–2050$140M
I-64 Auxiliary Lane - Exits 178-180 (both directions)Highways and roadsHenrico2038–2050$132M
US 360 Widening - Otterdale Rd to Magnolia Green PkwyHighways and roadsChesterfield2038–2050$128M
Darbytown Rd Widening - City Limits to Laburnum AveHighways and roadsHenrico2038–2050$123M
Route 10 Safety and Operation ImprovementsHighways and roadsChesterfield2038–2050$123M
W. Broad St - I-64 to Goochland LineHighways and roadsHenrico2038–2050$116M
Rural Point Rd Widening - US-301 to Studley RdHighways and roadsHanover2038–2050$94M
I-64 Auxiliary Lane - Exits 181-183Highways and roadsHenrico2038–2050$90M
Rt 288 (Rt 10 - Courthouse) WideningHighways and roadsChesterfield2038–2050$88M
Chippenham Pkwy at US-60/Midlothian Tpk InterchangeHighways and roadsMulti-Jurisdiction2038–2050$88M
Chippenham Pkwy at US-360/Hull St InterchangeHighways and roadsMulti-Jurisdiction2038–2050$88M
Route 1/Brook Rd Safety - Azalea Ave to HilliardHighways and roadsHenrico2038–2050$79M
Pemberton Rd Widening - Quioccasin Rd to US-250Highways and roadsHenrico2038–2050$74M
I-95 & Parham Rd Interchange ModificationHighways and roadsHenrico2038–2050$68M
Rural Point Rd Widening - Studley Rd to Pole Green RdHighways and roadsHanover2038–2050$65M
Springfield Rd Relocation - Francistown to Olde MillbrookeHighways and roadsHenrico2038–2050$65M
VA-150 & Hopkins Rd Interchange ModificationHighways and roadsChesterfield2038–2050$64M
U.S. Route 1 Safety - Ashcake Rd to Southern Town LimitHighways and roadsAshland2038–2050$62M
Three Chopt Rd Widening - Gaskins to ParhamHighways and roadsHenrico2038–2050$61M
Church Rd Widening - Three Chopt Rd to John Rolfe PkwyHighways and roadsHenrico2038–2050$59M
Shared Use Path: Eltham to LanexaWalking and bikingNew Kent2038–2050$57M
Shared Use Path: New Market Heights TrailWalking and bikingHenrico2038–2050$56M
Pole Green Rd Widening - Rural Point Rd to Walnut Grove RdHighways and roadsHanover2038–2050$55M
Shared Use Path: School Complex to New Kent Co. Line on Rte 155Walking and bikingCharles City2038–2050$54M
Shared Use Path: VCT to New Kent County Line on Rte 106Walking and bikingCharles City2038–2050$53M
Shared Use Path: Westham Trail - VA-150 to GoochlandWalking and bikingHenrico2038–2050$53M
Williamsburg Rd Safety - Randall Ave to Charles City RdHighways and roadsHenrico2038–2050$53M
New Ashcake Rd Extension to Air Park RdHighways and roadsHanover2038–2050$52M
I-295 Auxiliary Lane - I-64 WB on-ramp to Nuckols Rd SBHighways and roadsHenrico2038–2050$51M
Masonic Ln/Brittles Ln WideningHighways and roadsHenrico2038–2050$49M
I-64 Auxiliary Lane - Exits 183-185 WestboundHighways and roadsHenrico2038–2050$49M
I-64 Auxiliary Lane - Exits 183-185 EastboundHighways and roadsHenrico2038–2050$47M
Shared Use Path: Providence Forge to Lanexa along US-60Walking and bikingNew Kent2038–2050$46M
Creighton Rd Widening - Sandy Ln to Richmond City LimitsHighways and roadsHenrico2038–2050$44M
N Gayton Rd WideningHighways and roadsHenrico2038–2050$43M
US-60 & Belt Blvd Interchange ImprovementsHighways and roadsRichmond2038–2050$42M
Glenside Drive and Horsepen Road Safety ImprovementsHighways and roadsHenrico2038–2050$38M
Shared Use Path: Courthouse Rd to Charles City Co. LineWalking and bikingNew Kent2038–2050$35M
Meadowbridge Rd Widening - Henrico Co. Line to Atlee RdHighways and roadsHanover2038–2050$30M
I-64 WB Auxiliary Lane between Exits 185 and 186Highways and roadsMulti-Jurisdiction2038–2050$29M
Shared Use Path: New Kent Courthouse to Talleysville along 249Walking and bikingNew Kent2038–2050$29M
Shared Use Path: Talleysville to Charles City Co. LineWalking and bikingNew Kent2038–2050$29M
S. Laburnum Ave Safety - Williamsburg to Nine MileHighways and roadsHenrico2038–2050$28M
Parham Rd & Woodman Rd Intersection ImprovementsHighways and roadsHenrico2038–2050$28M
Charter Colony Pkwy (Rolling Spring - Woolridge) WideningHighways and roadsChesterfield2038–2050$28M
Shared Use Path: River Road West (Route 6)Walking and bikingGoochland2038–2050$27M
Courthouse Rd at Dakins Dr R-Cut and Bike/PedHighways and roadsChesterfield2038–2050$26M
Nine Mile Rd Safety - Dabbs House to LaburnumHighways and roadsHenrico2038–2050$26M
Route 106 Widening (2L to 4L): City Center/I-64 to Parrish RdHighways and roadsNew Kent2038–2050$26M
Parham Rd Safety - Holly Hill to Three ChoptHighways and roadsHenrico2038–2050$25M
Brandermill Pkwy Widening - Powhite Pkwy to Charter ColonyHighways and roadsChesterfield2038–2050$25M
W Broad St and Parham Rd Intersection ImprovementsHighways and roadsHenrico2038–2050$25M
Staples Mill Rd Widening - Hungary Springs to Mountain RdHighways and roadsHenrico2038–2050$24M
Mountain Rd - Shared Use PathWalking and bikingHenrico2038–2050$23M
Pouncey Tract Rd Widening - N Gayton Rd to Grey OaksHighways and roadsHenrico2038–2050$23M
VA-161 & Broad Rock BlvdHighways and roadsRichmond2038–2050$23M
Courthouse Rd at Cherylann Rd R-Cut & Bike/PedHighways and roadsChesterfield2038–2050$20M
Shared Use Path: RF&P Trails - Glen Allen to Glover ParkWalking and bikingHenrico2038–2050$19M
I-295 Interchange Modification - Exit 43 to C-D LaneHighways and roadsHenrico2038–2050$18M
Pouncey Tract Rd Widening - Nuckols Rd to Grey OaksHighways and roadsHenrico2038–2050$18M
Staples Mill Rd & Old Staples Mill IntersectionHighways and roadsHenrico2038–2050$18M
W Broad St and Parham Rd - Park and Ride & Transfer StationTransitHenrico2038–2050$18M
Willow Lawn Transfer FacilityTransitHenrico2038–2050$18M
Southside Transfer CenterTransitRichmond2038–2050$18M
VA Center Commons/I-295/I-95 - New Park and RidePark and rideHenrico2038–2050$15M
S Airport Dr Widening - Audubon Dr to Williamsburg RdHighways and roadsHenrico2038–2050$10M
Route 1/Willis Road Intersection ImprovementsHighways and roadsChesterfield2038–2050$9M
Lewistown Rd/Lakeridge Pkwy or Ashland Park and RidePark and rideHanover2038–2050$9M
Pouncey Tract Rd Widening - Henrico Co. Line to Ashland RdHighways and roadsHanover2038–2050$6M
"VA-161 Brookland Pkwy & Westwood Ave"RoadwayRepair program$0M
Manchester Bridge RehabilitationBridges (repair)—Repair program$30M–$47M
Lee Bridge RehabilitationBridges (repair)—Repair program$45M–$70M
Midlothian Turnpike Bridge RehabilitationBridges (repair)—Repair program$34M–$53M
Bridges (repair)—Repair program$135M–$210M
Rehabilitation or replacement of the Mayo BridgeBridges (repair)—Repair program$225M–$351M
Martin Luther King Jr Memorial Bridge RehabilitationBridges (repair)—Repair program$21M–$32M

Methodology

Plan. Pathways to the Future: Transportation 2050, the long-range plan of the Richmond Regional Transportation Planning Organization (staffed by PlanRVA). The board adopted it on September 10, 2026. Source: PlanRVA

Money. Revenue, maintenance, local and regional totals, and the committed-project amount are the grand totals in Technical Report I. All dollars are year-of-expenditure, so later years include inflation.

Projects. Mode, locality, time band and cost come from Appendix D of Technical Report I, parsed from the PDF. The parsed mode totals match the report: $7.9 billion in all. Two projects (a bus rapid transit extension and a transfer facility) have no map line, so the map shows 125 of 127.

Map. Project lines come from PlanRVA's own ArcGIS layer for the adopted plan, downloaded November 11, 2026. Basemap: OpenFreeMap, © OpenMapTiles, © OpenStreetMap contributors.

Not covered. The plan's unfunded vision list (67 projects), the four-year Transportation Improvement Program, and SMART SCALE applications.

Data. Projects as GeoJSON · Funding flow as JSON

Sources

  1. PlanRVA: Long-Range Transportation Plan (Transportation 2050)
  2. Pathways to the Future: Transportation 2050, final report (PDF)
  3. Technical Report I: Constrained Plan Development (PDF). Revenue totals, Appendix D project list
  4. PlanRVA ArcGIS layer: constrained plan projects